Time and Work: Work and Wages

Support this post with a reaction:

4,694 views

Practice Questions

Concept Explanation

When a fixed payment is shared, each worker's wage is proportional to work done.

Key Formulas

  • Wage share = (Individual rate / Sum of rates) × Total wage
  • Work done = Rate × Time; if time is equal, wages follow efficiency ratio
  • If A is twice as efficient as B, wage ratio A:B = 2:1 for equal time

Example

A and B finish work worth Rs. 1,200 together. A alone takes 12 days, B alone 18 days. Ratio of rates = 3:2. A gets Rs. 720, B gets Rs. 480.

Common Trap

Use work rates, not days directly. Fewer days means higher rate and larger wage share.