Time and Work: Alternate Day Work

Support this post with a reaction:

3,854 views

Practice Questions

Concept Explanation

When workers alternate days, add the work done in one full cycle (each worker's turn).

Key Formulas

  • Cycle work = sum of individual day rates in one round
  • Total days ≈ (number of full cycles × cycle length) + extra days
  • Starting worker affects which days count

Example

A alone 10 days, B alone 15 days, alternate from A. Two-day cycle = 1/10 + 1/15 = 1/6. The work is finished in 12 days.

Common Trap

Count partial cycles at the end; the last worker may not need a full day.