Time and Work: Basic Work Efficiency

Support this post with a reaction:

4,419 views

Practice Questions

Concept Explanation

Work = Rate × Time. Treat total work as 1 unit unless stated otherwise.

Key Formulas

  • If a person finishes in n days, daily rate = 1/n of the work.
  • Time = Work / Rate
  • Work done = Rate × Days worked

Example

A completes the work in 10 days. Daily rate = 1/10. In 4 days, work done = 4/10 = 2/5.

Common Trap

Do not multiply days directly unless rates are known. Always convert to work per day first.